At its Tuesday July 11, 2023 meeting, the county council approved the issuance of an $8 million bond for the Fullerton Pike bridge/road project. The new roadway will connect Gordon Pike to Fullerton Pike and I-69. It will run from the location of the new library project westward, over the Clear Creek Trail, and connect with Fullerton Pike, which has an interchange on I-69. |
The project to connect West Fullerton Pike to West Gordon Pike is finally getting started. It is expected to be complete by July 2026. It will include a traffic signal at the Fullerton Pike/Rockport road intersection; a roundabout at the Batchelor/Clear View/Gordon Pike intersection; a raised median measuring between 6 and 10 feet; a 10-foot multi-use path on the north side, a 5-foot sidewalk on the south side, and a 500-foot bridge.